Skip To Content

Menu

Division St at Duck Creek Bridge

Bridge Improvements on Division St at Duck Creek Bridge
Posted on 08/28/2020
Bridge Improvements on Division St at Duck Creek Bridge

08/28/20

Work on the Division St Bridge over #Davenport's Duck Creek is moving right along. With the northbound bridge deck complete, work has switched to the southbound lanes of the bridge.  One lane of travel in each direction will be maintained until the project is complete late September, early October. 

06/26/20

Check out the progress on the Division St Bridge over Duck Creek.  The northbound bridge deck and sidewalk have been removed, and structural support work continues.  The contractor will begin pouring the concrete deck mid-July.  Work is expected to transition to the southbound lanes in early August.

05/22/20
Repairs to the Division St Bridge over Duck Creek are set to begin Monday, June 1st.  Work will begin in the northbound lanes and then transition to the southbound lanes. One lane of head-to-head traffic will be maintained in each direction.

As part of the project, the contractor will be removing and replacing the bridge deck surface, replacing sidewalks and making structural repairs.

Bridge improvements are estimated to be complete around Friday, September 25th, pending weather.

Be aware travel delays are possible during construction.