Clark St Water Main and Reconstruction

Clark St Water Main and Reconstruction
Posted on 07/14/2023
Clark St Water Main and Reconstruction

07/14/23
Work is substantially complete and the road re-opened!

04/28/23
Water main work on Clark Street between 11th and 13th streets has been completed by Iowa American Water Company. Work has transitioned to street reconstruction.  The stretch will be open to one northbound only lane through the end of June while the pavement improvements are performed.

03/10/23
Next up in the construction season line-up – Clark St, between 11th and 13th Streets. As a coordinated project, initially work will close the entire stretch beginning March 8 for water main installation by Iowa American Water Company. The main installation is expected to last through May 15. Street reconstruction will follow the main installation and is expected to be complete by early July. The project will transition to one northbound lane when reconstruction begins.